Program cost (official)
$800M
Implementation ceiling on DND project page. Definition phase up to $90M. CAD.
Visual record Atmosphere for Griffon GLLE $800M Pause — Defence Procurement Investigation. Primary sources remain in the text. Powered by LIRIL AI.
In late June 2026, Ottawa paused the Royal Canadian Air Force CH-146 Griffon Limited Life Extension (GLLE) implementation — a program budgeted at up to $800 million after a definition phase of up to $90 million. DND says the pause allows reassessment of scope for cost, schedule, evolving complexity, and planning underway for a replacement fleet. This file freezes primary sources and places the pause in the four-point defence-procurement velocity/distortion cluster.
HIGH ACTIVE_INVESTIGATION DND · PSPC · Bell
$800M
Implementation ceiling on DND project page. Definition phase up to $90M. CAD.
85
CH-146 Griffon utility helicopters (official). Media pause coverage references ~82 under upgrade debate.
2027
Official schedule: contract 2022 · IOC 2024 · FOC 2027 · close-out 2028. Pause status supersedes certainty.
4 / 4
Fourth data point in velocity/distortion cluster (radar · submarine · GlobalEye · GLLE pause).
| Fact | Source class |
|---|---|
| GLLE intended to extend Griffon fleet life to at least 2031 via avionics, displays, engines, sensors, simulators, spares. | DND project page (primary) |
| Definition phase expenditure authority January 2019; Bell selected for definition design work 26 Jan 2019. | DND project page (primary) |
| Implementation ceiling published as “up to $800 million”; definition “up to $90 million”. | DND project page (primary) |
| June 2026: work paused; Bell notified; talks with DND and PSPC on upgrade-contract scope. | CBC News reporting (Murray Brewster, 27 Jun 2026) |
| DND: pause “to allow for a reassessment of scope in light of cost, schedule, evolving complexity and planning underway for a replacement fleet.” | Laura McIntyre-Grills, DND (via CBC) |
| Separate Bell in-service support contract valued at more than $2B (Jan 2024 reporting) to sustain fleet into mid-2030s. | Secondary defence reporting — verify against contract notice |
Primary: canada.ca — CH-146 Griffon Limited Life Extension · Reporting: CBC — upgrade on hold · Machine dossier: griffon_glle_investigation.json
GLLE is not an isolated delay story. Prior TENET5 overnight briefs already tracked sole-source and accelerated defence buys (Arctic OTHR framing, submarine competition timeline, L3Harris/Saab GlobalEye). A life-extension pause that explicitly cites replacement fleet planning adds a pause/pivot mode: money and schedule pressure can convert a capped $800M sustainment path into a multibillion-dollar replacement path without a clear public options analysis. That is the investigative core — not whether helicopters need upgrades.
Disclaimer: pattern notes are investigative hypotheses. Re-verify every figure against primary documents before legal use. Map: open the Defence instruments tab on the network board for the procurement cluster.